Project Background
An industrial logistics company required a large-scale warehouse facility in Hubli for their expanding distribution operations. The building needed to withstand heavy machinery loads, extreme weather conditions, and provide long-term durability with minimal maintenance.
Technical Requirements
- High compressive strength (≥ 100 kg/cm²) for load-bearing walls
- Low water absorption to resist monsoon moisture and prevent seepage
- Fire-resistant construction for safety compliance
- 6-inch thick walls throughout for structural stability
- Large volume supply with consistent quality across 3.5 lakh bricks
Mounto Bricks Solution
We supplied our 6-inch Special Perforated Bricks (9×6×6) for the external and load-bearing walls. The perforated design was chosen for several reasons:
Reduced Dead Load
Perforated bricks reduced wall weight by 25%, allowing a more economical foundation design for the 40,000 sq. ft. structure.
Temperature Control
The air cavities in perforated bricks kept the warehouse cooler by 4-5°C, critical for storing temperature-sensitive goods.
Delivery & Execution
The project required a staggered delivery of 3,50,000+ bricks over 60 days. We deployed a dedicated fleet and coordinated delivery schedules with the site engineer to ensure bricks arrived exactly when needed, minimizing on-site storage requirements and potential wastage.
Impact
Reduction in foundation costs
Cooler than comparable warehouses
Delivery delays across 60 days
"We needed a brick supplier who could handle industrial-scale volumes without quality drops. Mounto Bricks delivered 3.5 lakh bricks over 60 days, and every single batch met our specifications. The perforated bricks were a game-changer for our warehouse — significantly cooler interiors and a lighter structure."
— Mr. Sanjay Desai, Director, Desai Logistics Pvt. Ltd.